MGX’s Driftwood PEA pegs pretax NPV at $529.9M

Mar 6, 2018

2018-03-06 06:11 ET – News Release

Mr. Jared Lazerson reports

MGX MINERALS ANNOUNCES POSITIVE PEA FOR DRIFTWOOD CREEK MAGNESIUM; PRE-TAX NPV OF C$529.8 MILLION AND 24.5% IRR

MGX Minerals Inc. has released results of an independent technical report prepared in accordance with CIM (Canadian Institute of Mining, Metallurgy and Petroleum) guidelines and National Instrument 43-101 definition of a preliminary economic assessment (PEA) on its Driftwood Creek magnesium project.

The PEA study was prepared by AKF Mining Services Inc. (AKF), Tuun Consulting Inc. (Tuun), Samuel Engineering Inc. (Samuel), and will be filed on the Company’s SEDAR profile at www.sedar.com as well as available on the Company’s website at www.mgxminerals.com within 45 days.

The PEA presumes a conventional quarry pit operation with a process plant and a furnace/kiln combination to produce a saleable Dead burn magnesium oxide (DBM) product. The plant will also have the ability to produce Caustic-calcined magnesium oxide (CCM) as a separate salable product. All dollar amounts in this release are stated in Canadian currency.

HIGHLIGHTS

Highlights of the PEA include the following:

  • Pre-tax NPV@5% of $529.8 million, IRR of 24.5% with a 3.5-year payback
  • Post-tax NPV@5% of $316.7million, IRR of 19.3% with a 4.0-year payback
  • Initial capital costs of $235.9 million (Total life-of mine (“LOM”) – $239.8 includes sustaining/closure costs of $3.9 million and contingency costs of $40.0 million)
  • Conventional quarry pit mine with a 1200 tonne per day (“tpd”) process plant using conventional crushing, grinding, flotation upgrading, calcination, and sintering to produce a saleable DBM product
  • Cash costs of $350/tonne MgO
  • All-in sustaining costs (“AISC”) of $351/tonne MgO
  • Average annual MgO production of 169,700 tonnes during an 19 year mine life
  • LOM average head grades of 43.27% MgO
  • LOM MgO recoveries of 90% LOM strip ratio of 2.4 to 1 of rock to mineralized material

The reader is advised that the preliminary economic assessment summarized in this press release is only intended to provide an initial, high-level review of the project. The PEA mine plan and economic model include the use of inferred mineral resources which are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the preliminary economic assessment will be realized.

“We are extremely pleased with results of the PEA, which display Driftwood’s ability to become a high-margin, low-cost producer of magnesium oxide in a politically secure jurisdiction,” stated MGX President and CEO Jared Lazerson. “We believe this significant milestone outlines a clear path forward and provides numerous opportunities to further enhance the economics of the Project with a pre-feasibility study.”

PEA SUMMARY OF RESULTS
 
 Summary of Results                         
Mine Life                  Years      18.8 
Total Resource             M tonnes   7.8  
Total Waste                M tonnes   19.1 
Total Capitalized Waste    M tonnes   0.1  
Total Mined                M tonnes   27.0 
Strip Ratio                w:o        2.44 
Mining Rate                tpd        4,103
Plant Throughput           tpd        1,200
Pre-Strip/Capitalized WasteM tonnes   0.1  
Average Head Grades                        
MgO                        %          43.27
CaO                        %          1.00 
Al2O3                      %          1.00 
SiO2                       %          4.88 
Fe2O3                      %          1.34 
LOI                        %          47.92
Payable Metal                              
MgO                        LOM k tonne3,055
                           k tonne/yr 169.7


   SUMMARY OF ECONOMICS
 
 Pre-Tax Cash Flow during Production            $M   $ 1,051 
Avg Pre-Tax Cash Flow per Year                 $M   $ 72.6  
Taxes                                          $M   $ 391.8 
Post-Tax Cash Flow during Production           $M   $ 659.4 
Avg Post-Tax Cash Flow per Year                $M   $ 50.9  
                                                            
Discount Rate                                       5 %     
Pre-Tax NPV ($M)                                    $ 529.8 
Pre-Tax IRR                                         24.5 %  
Pre-Tax Payback (Yrs)                               3.5     
Post-Tax NPV ($M)                                   $ 316.7 
Post-Tax IRR                                        19.3 %  
Post-Tax Payback (Yrs)                              4.0     
                                                            
MgO Cash Cost (CAD $/tonne)                         $ 350.0 
MgO Cash Cost incl. Sustaining Capital (CAD $/tonne)$ 351.3 


The PEA mine plan and economic model include the use of inferred resources which are considered to be too speculative to be used in an economic analysis except as permitted by NI 43-101 for use in PEA’s. There is no guarantee that inferred resources can be converted to indicated or measured resources and, as such, there is no guarantee that the project economics described herein will be achieved. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

CAPITAL AND OPERATING COSTS SUMMARY
 
 Capital Cost                        Pre-Production ($M)Sustaining/Closure ($M)LOM $M 
                                                                                     
                                                                                     
EA, Permitting, Basic Engineering   6.8                0.0                    6.8    
Capitalized Stripping - Waste       0.5                0.0                    0.5    
Capitalized Stripping - Organics    0.3                0.0                    0.3    
Mine Site & Development             1.5                0.0                    1.5    
Plant Site (Cranbrook, BC Property) 3.8                0.0                    3.8    
Process Plant                       37.7               0.4                    38.1   
MgO Calcination                     108.7              0.4                    109.1  
EPCM                                14.4               0.0                    14.4   
Indirects                           15.9               0.0                    15.9   
Reclamation/Closure                 0.0                2.5                    2.5    
Owners Costs                        7.1                0.0                    7.1    
Subtotal                            196.6              3.3                    199.9  
Contingency                         39.3               0.7                    40.0   
Total Capital Costs                 235.9              3.9                    239.8  


Operating Costs Summary

  
 
 Cost                   
                             $/t ProcessedLOM $M$M/a
Mining{A  ‡}                      30.30        237.7 13.2
Transport from Mine to Plant 43.95        344.7 19.2
Processing + G&A             62.06        486.8 27.0
Total                        136.31       1,069 59.4


{A ‡}Mining Cost is based on $8.82/t mined

Project Description

The Driftwood Creek Project is located in the southern British Columbia (BC), Canada. The mine site property is located approximately 210 km northwest of Cranbrook, BC. Infrastructure currently exists in the form of paved highways and forest service roads, a CPR spur line (at Brisco, BC), and a major power line within 15 km of the property. The plant will be located in Cranbrook, BC, where all mineralize run-of-mine (ROM) material will be hauled and processed.

Mining is via conventional quarry pit methods. Mining will be contracted so no capital is included for mining equipment; instead a contractor mining quote was used as the basis for mining costs. Mining costs were calculated from first principles based on equipment required and include pit and dump operations, supervision and technical services, and fuel costs.

Processing will be a conventional crushing, grinding, flotation upgrading, calcination, and sintering to produce a saleable DBM product.

Transportation of mineralized run-of-mine (ROM) material will be hauled via a 40-tonne highway truck from the mine to plant site located in Cranbrook, BC. No capital is included for highway trucks; instead contractor haul quote was used as the basis for the transportations costs which includes fuel and ROM loading.

Mineral Resource Estimate

The Mineral Resource has been prepared by Tuun Consulting Inc. (Tuun) based upon forty-nine (49) diamond drill holes, the twenty-five percussion (25) blast holes used for the bulk sample, and 45 magnesite surface samples. This resource estimation was completed by Allan Reeves, P. Geo., an independent qualified person as defined in NI 43-101. The effective date of the resource statement is December 31st, 2016.

The resources estimated are considered a reasonable representation of the Driftwood Creek Magnesite Project at the current level of prospecting and sampling. The estimate follows the CIM Definition Standards for Mineral Resources and Mineral Reserves (as adopted by CIM Council on May 10th, 2014).

The tonnage and grades of the Driftwood Creek Project mineral resource at a 42.5% MgO cut off are shown in the table below:

 Class    Tonnes   ({A  ‘}000s)MgO  (%)Al2O3  (%)CaO  (%)Fe2O3  (%)SiO2  (%)LOI  (%)
Measured 4,702.7         43.31   1.01      0.95    1.29      5.06     47.83   
Indicated3144.4          43.22   1.00      1.05    1.42      4.67     47.99   
M&I      7,847.1         43.27   1.00      0.99    1.35      4.90     47.89   
Inferred 55.8            42.95   0.93      0.66    1.43      6.07     47.46   


Mine Development and Operations

The proposed project concept is to develop a green-fields DBM deposit with conventional quarry mine with 1200 tonne per day (“tpd”) ROM hauled to the plant site, located in Cranbrook, BC.

All mining operations (drill, blast, load and haul) will be done by contractors. Also, the mineralized ROM haul and loading will be completed by contractors.

The PEA forecasts a 19 year mine life and a LOM strip ratio (the ratio of rock to mineralized material) of 2.4 to 1. A total of 7.84 million tonnes of mineralized resource could be mined and processed with 19.174 million tonnes of rock material which includes 60,000 tonnes of capitalized rock.

Metallurgy and Processing

Mineralized material will undergo crushing, grinding, flotation upgrading, calcination, and sintering to produce a saleable dead burned magnesium (DBM) product. The plant will also have the ability to produce caustic calcined magnesia (CCM) as a separate product.

Mill throughput is designed at 1200 tonnes per day. The plant is expected to achieve an average recovery of 90 percent with a magnesium oxide (MgO) purity of 94.6 percent. The DBM product will be bagged and transported to market for sale as a powder.

Dewatered tails will be trucked back to the mine site quarry for dry stacking in a tailings storage facility.

Environment, Permitting and Corporate Social Responsibility

The project area is not within a known environmental protection area. Formal environmental baseline and social impacts studies have not been initiated but will be required to obtain the environmental permits for future mining operations.

PEA Contributors

The technical information in this news release has been prepared in accordance with Canadian regulatory requirements set out in NI 43-101 and reviewed by the following Qualified Persons:

Allan Reeves P.Geo., Tuun – Geology and Mineral Resource Estimation

Antonio Loschiavo, P.Eng., AKF {A –} Mining, Infrastructure, Environmental Studies, Permitting, Social & Economics

Matt R. Bender, P.E., Samuel Engineering {A –} Metallurgical and Recovery Methods

The authors of the PEA have approved the disclosure of the scientific or technical information contained in this news release.

Qualified Persons

The technical portions of this press release were reviewed by Andris Kikauka (P. Geo.), Vice President of Exploration for MGX Minerals. Mr. Kikauka is a non-independent Qualified Person within the meaning of National Instrument 43-101 Standards.

About MGX Minerals

MGX Minerals is a diversified Canadian resource company with interests in advanced material and energy assets throughout North America. Learn more at www.mgxminerals.com.

We seek Safe Harbor.

https://www.mgxminerals.com/investors/news/2018.html

Related Posts

Tags

Share This