Contact Exploration Announces Participation in New Acreage and Well; Provides Montney Operations Update
Contact’s second operated Montney well (the “14-30 Well”) has been successfully tied into downstream processing facilities. In January 2013, the 14-30 Well was flowed for only a brief period, due to the third party gas plant not having capacity for the extremely high levels of free flowing condensate (in excess of 200bbl/mmcf of natural gas) from the well. Contact’s third operated Montney well (the “3-19 Well”) is being drilled from the same surface location as the 14-30 Well, with drilling on schedule to be finished in mid-February 2013, with completion operations anticipated to be finished by mid-March 2013. Once completion operations on the 3-19 Well are finished, the Company will equip the 14-30 and 3-19 Wells in similar fashion to the 13-17 Well, such that condensate can be separated at location, allowing for flow of natural gas from these wells to the third party facility and for condensate to be trucked directly to the sales point. Contact has a 25% interest in both the 14-30 and 3-19 Wells.